This past week (05.31.22 - 06.03.2022):
Chase completed installation of watermain on Washington Ave and all the tie ins. Sewer has been completed per plans except one service that was found Friday, June 3rd. Storm drain is almost complete. One structure is left and three short storm drain runs are left. Chase began box cutting the road at the intersections of the side streets and placed D gravel ramps for their trucks to get in and out.
Next week (06.06.2022 -06.10.2022)
Chase plans to connect the last sewer service to the main. They will do additional sewer work on Washington Ave. They will continue storm drain when they can. They may start placing D gravel on Washington Ave.